PROJECTS

Completed Projects

Silverthorn Pumping Station Reservoir

Mississauga, Ontario | Completed September 2022

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
Image Slide 6
previous arrow
next arrow

Scope of Project:

The work involved expanding the Silverthorn Pumping Station water facility by constructing a new Pump Station Building between existing Generator & Existing Pump Station Facility. New Pump Station complete with new Pump room, basement, and electrical room. Relocation of water mains and electrical duct banks was done to accommodate the expansion. Shoring and caisson systems were installed to support existing infrastructure.

The work also Included:

    • Installation of high lift pumps and retrofitting of existing pumps

    • Replacement of High Voltage Primary Switchgear

    • Demolition and removal of existing equipment after commissioning of new area

    • No interruption to the existing station and infrastructure during testing and commissioning

Britannia LPS, O’Neil / Shardawn Mews SPS Upgrades

Mississauga, Ontario | January 2021

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrow
next arrow

Scope of Project:

The project involves upgrading three existing live sewage pumping stations (Britannia LPS, O’Neil SPS, and Shardawn SPS) in Mississauga. Long-term bypass systems were provided at each site for completing upgrades in the wet well and sewage pump stations. The bypass systems included duty pumps (electric and/or diesel), standby pump, temporary generator, and auto-dialer for 24/7 monitoring.

The work also included:

  • Britannia SPS:

    • Installation of dewatering system and slide rail shoring system for safe excavation of new precast meter chamber

    • Installation of underground force main and drain piping from metering chamber to existing wet well

  • Shardawn Mews SPS:

    • Installation of slide rail shoring system and new emergency precast storage chamber in limited space within residential roadway

    • Installation of precast sewage grinder manhole over live sewage

Foxboro WWTP Upgrades

Baden, Ontario | Completed December 2018

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
previous arrow
next arrow

Scope of Project:

The project involved refurbishing the Foxboro WWTP Biological Contactor Treatment Trains and providing short-term bypass systems for effluent pump replacement. Demolition of existing components in the RBCs was done in phases, followed by retrofitting of each RBC tank and installation of pre-purchased MBBR systems.

The work also included:

  • Provide precast Prefab Odour Control & Electrical Builds

  • Electrical & Instrumentations

  • SCADA upgrades/ SAT testing/ Commissioning & Performance Testing

Waterloo WWTP Maintenance Building

Waterloo, Ontario | Completed July 2018

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
Image Slide 7
Image Slide 8
Image Slide 9
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
Image Slide 7
Image Slide 8
Image Slide 9
previous arrow
next arrow

Scope of Project:

The project involved the removal and demolition of existing equipment, building structures, and a portion of the reinforced concrete foundation at the abandoned Influent Pumping Station. Additionally, a maintenance building was constructed on the same site. It also featured a mezzanine, aluminum siding for the exterior finish, a crane rail system with a hoist, HVAC, plumbing, and building electrical systems.

The work also included:

  • Installation of new underground water lines, sanitary sewers, and storm sewers to serve the new building

  • Adjustment of site grading to accommodate the construction of the building and a new driveway.

  • Incorporation of a crane rail system with a hoist in the maintenance building

Mill Street and Carl Crescent WWPS

Completed in 2017

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrow
next arrow

Scope of project:  

  • Setup Bypass System to bypass flow to complete retrofits and upgrades

  • Remove existing lid of wet well chamber and replace with new

  • Remove all internals (process piping, pumps, electrical, etc)

  • Installation of temporary structures, controls and power for control and operation of pump stations during the entire construction period 24/7

  • Demolition and removals (architectural, structural, mechanical, process, instrumentation, and electrical) of buildings

  • Excavation including rock breaking to 11.5m deep beside existing live pump station

  • Construction of new sanitary sewers and manholes including tie-ins to existing force mains at both pump stations

  • Construction of new buildings including concrete, masonry, access platforms, ladders, roof, piping & valve assemblies, HVAC, Electrical, etc

  • Commissioning and training for equipment installed at both pump stations

Binbrook Library

Completed in 2017

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrow
next arrow

Scope of Project:

  • Demolition of existing 3000 square foot Binbrook library

  • Construction of 6000 square foot library

  • New sewers, gas lines, sanitary and water-main

  • Asphalt paving and landscaping

MacNab Transit Station

Completed in 2012

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
previous arrow
next arrow

Scope of project:

  • Construction of new Transit Terminal in Downtown

  • Demolition of existing road, structures, retaining walls, curbs, sidewalks and canopy shelters

  • Construction of counterfort retaining walls

  • Concrete ramp rehabilitation

  • Site landscaping and irrigation system

Seaway Waste Water Treatment Plant

Completed in 2011

Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
Image Slide 7
previous arrowprevious arrow
next arrownext arrow
Image Slide 1
Image Slide 2
Image Slide 3
Image Slide 4
Image Slide 5
Image Slide 6
Image Slide 7
previous arrow
next arrow

Scope of Work:

  • Construction of upgrade and & expansion of wastewater treatment plant

  • Construction of 3 new primary clarifiers, pump gallery, new headworks building, and inlet channel with associated equipment

  • Retrofit of existing aeration tank including installation of outlet gates & fine bubble aeration system

  • Installation of air pipeline between existing headworks & aeration tanks

  • Upgrade of existing chlorine chamber from storm water chlorination

  • Commissioning and performance testing of all equipment supplies and installed

McVean Sewage Pump Station

Completed in 2008

Image Slide 1
Image Slide 1
previous arrow
next arrow

Scope of Project:

  • Construct new sewage pumping station
  • Construction of new concrete biofilter c/w associated equipment, chambers, steam generators, pumps, and piping
  • Construction of Force Main and sanitary sewers with associated manholes and temporary sewage pumping to bypass the 1500mm sanitary sewer during construction of 1650mm sanitary sewer
  • Watertightness testing
  • Demolition of existing pump station
  • Site restoration